Southeast Missouri State University

Construction Updates

Academic Hall

Scope of Work

Replace failing infrastructure; retain historical elements; enhance the student experience via One-Stop concept. 

  • Painting continues
  • Telecom continues with installation of cabling
  • Ceiling grid installation in progress
Dome Fit-Out
  • Awaiting contractor pricing

Housing and Greek Village Master Plan

Scope of Work

Obtain master plan services from architects and engineers to determine needs/direction for all residence halls and feasibility of construction of a Greek Village.

  • Survey complete
  • Report indicates project not feasible as suggested

Magill Hall Renovation

Scope of Work

Replace antiquated HVAC systems, improve energy efficiency, remediate hazardous materials, correct accessibility issues, and renovate entire building.

Phase 2A - Renovation
  • Punch-list items are nearly complete
  • Most of the new furniture has arrived
  • The IT casework has been completed

MMTF Nexus

Scope of Work

Design and construction of new Nexus Facility and Bike Station Facility at MMTF location.

  • MoDot is reviewing two lowest bids

New On-Campus Housing

Scope of Work

Provide 200-250 bed residence hall on campus and a possible four building Greek Village to the northeast of OVC Fields.

  • Project will be bid in two phases
    • Phase I will include site and utilities
    • Phase II will include the main building
Phase I
  • Phase complete
Phase II
  • Finishing painting and ceramic tile
  • Final elevator inspection is scheduled
  • Trees have been planted

Boiler Plant – Natural Gas Boiler Installation

Scope of Work

Replacement of existing coal boilers with gas fired boilers, to minimize emissions and to be more efficient. Additional work to be done as well to dismantle and remove a boiler.

Phase 3
  • Replacing tunnel lid in Boiler Plant
  • Work to be completed by August

River Campus Expansion

Scope of Work

Construct additional classroom, residential, food service and parking at existing River Campus site. 

  • Reviewing plans

Scully Building HVAC and Controls

Scope of Work

Install new HVAC system and controls for entire Scully Building.

  • To be completed in two phases
    • Phase I will include construction of the first and third floors during summer 2012
    • Phase II will include construction of the second and fourth floors during summer 2013

Phase II
  • Duct insulation is 75% complete
  • Pipe insulation is 50% complete
  • Control work is 20% complete

Show Me Center Chiller Plant

Scope of Work

Provide new chiller plant for Show Me Center, Student Rec Center - North, and Student Aquatic Center, to be completed in conjunction with the New Residence Hall.

  • Demolition of piping in mechanical room is underway
  • Chilled water tie-in will begin in early July
  • Steam tie-in will begin mid-July